We’re getting new counters, stalls, and tile in the public restrooms. The project begins March 2nd. Here’s what to expect.
Restrooms will be closed beginning March 2nd. Three portable toilets (one handicap accessible) will be delivered outside the Commons doors. Plumbers will remove the sinks and toilets. Two private diaper changing stations will be setup: one in the Commons and the other near the Youth Computer Lounge.
Tile tear-out and installation will begin the week of March 9th and extend to March 30th or April 6th.
Once the tile is done, toilets and sinks will be be put back, and new stall doors and counters will be installed.
Everything should be done by the second week of April.
The staff restroom will be open throughout.